Tile Time!

While I would like to throw out excuses as to why you haven’t seen a post from me lately (perhaps the recent debut of the Game of Thrones or the cunning way my dog dictates my ‘play’ schedule), but the reality is that putting up tile takes a long time!

I mean, sure, you can slap up some mortar and stick some tiles to the wall in no time, but what you’re left with would cause anyone with even moderate OCD to fly into a fit of rage.

badtile

As someone who appreciates clean and level lines, I decided that I would take my time putting the tile up the “right way.”  Now, you might be asking “Beth, what IS the right way to put up tile?”  Well, blog reader, as someone who has just completed her first tile job, I’m a wealth of information.  Okay, perhaps I’m more like a coin jar of information.  Regardless, here’s what I learned:

 

 Step 1:  Waterproof your tub surround

Awhile back I had a “tile guy” come out and install a mortar bed around the tub.  The reasoning for this was twofold.

 Reason #1:  None of the walls around the tub were square or plumb.  If I were to just slap up some concrete board and install the tile, the crooked lines would have caused immediate and unstoppable twitching that would have eventually provoked  the beast within to emerge and completely destroy the bathroom.  Clearly, this would have been counterproductive & put my work behind schedule.  A mortar bed is essentially putting a concrete like substance up on the wall and then molding those walls until they are square and plumb.

 Reason #2:  The mortar bed is completely waterproof!  No need for any additional liner, waterproof membrane or anything else.

Now that we have our bathtub surround waterproofed and square, it’s time to get down to business!

 

rightangle

Step 2:  Select Your Tile:

One of the reasons this tile job took me around a month to complete was because I selected subway tile.  The smaller the tile, the more time it takes to ensure everything is level, and the more cuts you need to make.  For those of you considering doing some tiling, but are working on a tight timeline, I do not recommend working with subway tile (although it is beautiful!)

We decided to go with a sea-foam green glass subway tile.  The glass is slightly rippled, making it look refreshing and wet (two adjectives that seem at home when describing a bathroom)

tile1

tile2

 

Step 3:  Get your Materials:

For this job I got the following items:

  1.  Tile
  2. Mortar specifically for glass tile
  3. Polymer additive for mortar (this makes it a little extra water proof)
  4. Tile Spacers
  5. Notched Trowel
  6. Grout Float
  7. Sponge
  8. Level
  9. Bucket for mixing
  10. Tile Cutting saw.  (I decided to buy a cheap $80 saw rather than rent one for $50 a day.  It was an excellent purchase and I highly recommend others do the same.  At $50/day to rent, by the time you’re done you could have bought a fancy tile cutting saw.  I got the Skil 7″ Wet Tile Saw at Lowes.     It is the Easy Bake Oven of tile saws, but it worked great for my needs.

skilsaw

 

Step 4:  Planning

The most important row of tile you’ll lay is the first one.  That first row needs to be perfectly level in order for the rest of the wall to follow in its footsteps.  If your first line of tile is off level by even a fraction of an inch, by the time you get to the top of the wall you could be off by inches.

I started my planning by marking the center of the walls (vertically and horizontally) with level lines as guides.

 

guidelines

 

marks

 

 

Step 5:  Mix It Up!

Okay, I have everything I need, and now it’s time for tiling.  Much like working with concrete, I had to get the mortar all mixed up:

mix

 

Step 6:  Start Tiling!

I begin by placing my first tile directly to the left of the center line.

centerline

The idea behind working off the vertical center line is that by the time you get to the end of the line, you’ll be left with a ½ a tile (if you measured correctly).  When you start working in the other direction, by the time you get to the end you can use that remaining ½ a tile to finish up the row.  This saves you time on cuts and money on wasted tile.

When I do the 2nd row, I will place my tile directly in the center of the vertical line, thus alternating the tile seams.  From there, you just keep on building up until you’re done with the wall.

3rows

6rows

9 rows

Step 7:  Start Tiling the Side Wall

When working on the side walls, not only does the first row need to be perfectly level (just like the wall you just finished), but the tiles should appear to wrap around in a continuous line.

wrap around

 

 

Step 8:  Cleaning

Now that all of the tile has been installed and allowed time to dry, it’s time to clean between the tiles so the grout can fill those holes.

Mortar is a very hard substance when it dries, so to clean between the tile lines you may need to use an X-acto knife.  I also used 0000 steel wool to clean the mortar off the glass without scratching it.

all

 Step 9:  Grouting

You mix your grout in a similar way as you did with the mortar.  Once it’s ready to be installed, you use your grout float to spread the grout between the lines of the tile at an angle.  You work your way down the tile, making sure to fill every crevasse.   Once you’re done with the initial installation, you let it dry for about 20 minutes and then scrub the excess off with a sponge.

wipe

wipe2

After cleaning the excess grout off with a damp sponge you may be left with a light film on the surface of the tile.  This film can be easily wiped away with a damp sponge.

hazy

hazy2

Step 10:  Polish

Once you’ve cleaned the grout film off, you’re left with this beautiful final product!  It may take awhile to get here, but it’s well worth the time and energy!

final2

final3

final1

 

 

finish2

 

Advertisement
5 comments
  1. Meg said:

    The tile is breathtaking in person and looks absolutely gorgeous! Awesome job craftswoman Beth!

  2. n0r1 said:

    Beautiful! Nicely done, Beth. 🙂

  3. n0r1 said:

    Looks just gorgeous! Nicely done, Beth. 🙂

  4. tamsen munger said:

    What a project! great job

  5. Terry said:

    Beth, we saw the tile “in process” as you were doing it….. it was painstaking, partly because you were being so careful and precise. It now looks great, so congrats. Also, I saw you cutting some of the tile…. I’m real glad you did not cut yourself in the process — again, you were being patient and precise. Terry

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: